Stage | Timeline | Normal Progressive Scheme (NPS) % of Purchase Price |
Upon the grant of Option to Purchase | Option Date | 5% |
Upon signing the Sales & Purchase Agreement (S&P) | 8 weeks from Option Date | 15% |
Completion of Foundation work | 6-9 months | 10% |
Completion of Reinforced Concrete Framework | 6-9 months | 10% |
Completion of Brick walls | 3-6 months | 5% |
Completion of Roofing/Ceiling | 3-6 months | 5% |
Completion of Electrical Wiring Internal Plastering, Plumbing & Installation of Door & Window Frames | 3-6 months | 5% |
Completion of Car Park, Roads and Drains Servicing the Housing Project | 3-6 months | 5% |
Notice of Vacant Possession | TOP | 25% |
Legal Completion Date | CSC | 15% |